Solar site assessment and system design

Before MTR can install the panels, we need to design a system that fits your roof. This almost always involves visiting your home for an assessment. We need to ensure that your roof won't need replacing before installation and that it isn't too shaded by trees or other buildings. If your house needs a new roof or trees need to be trimmed, your timeline is going to get a bit longer.

Permits

After you sign off on your solar system design, your city or local authority needs to as well. From the time we submit the necessary plans to the time of installation depends on the permitting process but you can plan 3-6 weeks.

Installation

Perhaps the most exciting part of the solar installation process is also one of the quickest. Installation -- when workers are on your roof attaching panels -- takes only a few days, even for complicated jobs. Expect it to be done in three to five days or fewer.